Vestas Receives 99 MW Order For New Hampshire Project

0

Vestas has received an order for 33 V90 3 MW wind turbines for the Granite Reliable Power Windpark in New Hampshire. The 99 MW project is majority-owned by Essex, Conn.-based Noble Environmental Power.

The turbines are expected to be delivered in the first half of 2011, with project commissioning scheduled for the second half of 2011. The Granite Reliable Power Windpark is currently under development in Coos County. The order also includes a two-year service and maintenance agreement.

This is Vestas' second major project in New England. The company supplied 22 V90 3 MW turbines for the Kibby I project in Maine that went online in October 2009, and is currently installing an additional 22 V90 3 MW units for Kibby II. Commissioning is expected in the first half of this year.


SOURCE: Vestas Wind Systems