Juhl Wind Completes Construction Of Danielson Wind Project

0

Juhl Wind Inc. has completed construction of its 19.8 MW Danielson wind project in Meeker County, Minn. The project, which cost approximately $42 million, was completed on time and under budget, according to the developer.

This facility was built in conjunction with the 19.8 MW Adams wind project, also located in Meeker County, Minn. Juhl Wind served as the developer and owner's representative for the construction phase for both of the projects.

The Danielson project consists of 12 Alstom ECO 86 wind turbines and will sell the energy to Xcel Energy under a 20-year power purchase agreement.

SOURCE: Juhl Wind Inc.