Iowa Wind Project Making Use Of Manitowoc Cranes

0

Manitowoc says nearly a dozen of its crawler cranes and several Grove RTs have been involved in the development of the 443.9 MW Rolling Hills Wind Project in southwestern Iowa.

Helping to erect 193 wind turbines are three Manitowoc 16000s, each with a wind attachment; two Manitowoc 14000s; two Manitowoc 888s; two Manitowoc 2250s; and several Grove rough-terrain cranes.

Site preparation for the Rolling Hills Wind Project began in April 2011, and turbine erection should be complete by November.