South Dakota PUC Approves Permit for Crowned Ridge Wind II

0

The South Dakota Public Utilities Commission (PUC) has approved a construction permit for the Crowned Ridge Wind II Project, a 301 MW wind energy facility to be constructed in Codington, Deuel and Grant counties, S.D. 

PUC staff and Crowned Ridge presented nearly 50 proposed conditions that addressed issues including shadow flicker, ice throw, land restoration, the hiring of a public liaison officer and decommissioning.

Commissioners delved into a lengthy discussion on those and other issues, making changes to proposed conditions and adding new conditions. Some proposed conditions that were changed and added relate to aircraft detection lighting systems, cooperation with agricultural spray applicators, monitoring sound pressure levels, avian and bat mortality monitoring, and monitoring for whooping cranes.


“Intervenors did a great job working through a process that many past intervenors have found hard to navigate,” says Gary Hanson, PUC chairman. 

“We certainly must protect citizens, and we have to follow the law. In this docket, I believe we did as much as our authority allows to set conditions that protect landowners this project will affect,” he adds.

Crowned Ridge Wind II will consist of up to 132 wind turbines and span approximately 60,996 acres east of Watertown. Currently, the project is expected to be constructed in two phases. The first phase consists of 200 MW, which the company expects to construct in 2020 and has entered into a purchase and sale agreement with Xcel Energy to sell to Xcel upon commercial operation. The second phase may consist of 100 MW and is awaiting transmission interconnection study results. The total cost of the project is $425 million.

The proposed project will interconnect to the electric grid at the Big Stone South 230 kV substation using the Crowned Ridge II five-mile, 230 kV transmission line and the Crowned Ridge 34-mile generation tie-in line. Applications for the transmission and generation tie lines were both previously approved by the PUC. Construction of both lines was completed in 2019 in anticipation of the Crowned Ridge Wind II project.

Photo: Map is representative of project location but is not to scale and the icon does not indicate actual project boundaries

Subscribe
Notify of
guest
0 Comments
newest
oldest most voted
Inline Feedbacks
View all comments