Puget Sound Energy has signed a 25-year PPA with Clearway Energy Group for a 315 MW wind farm under development in Wheatland and Meagher counties in Montana.
“This agreement with Clearway helps us meet some of the most ambitious clean energy laws in the nation while delivering on our customer’s expectations for energy that is safe, reliable and affordable,” says Ron Roberts, PSE’s senior vice president of energy resources.
“We are proud to be a partner in developing Montana’s wind resources. This project is another milestone in our continued investment in the state’s energy economy.”
The Haymaker Wind facility is being developed by Clearway. Construction is expected to start in 2026, with completion and commercial operation targeted for 2028.
Wind energy from Haymaker will be delivered to PSE’s customers using existing PSE transmission.