Iberdrola Completes First Phase of Saint-Brieuc Offshore Wind Farm

0

Iberdrola is progressing according to plan in its construction project in the waters off Brittany in France for the Saint-Brieuc offshore wind farm. The company has completed the first campaign of the works with the installation of 65% of the piles and 40% of the offshore wind platforms of the plant. These elements have been manufactured at Windar’s facilities in Avilés and Navantia’s in Fene, respectively.

In total, 124 piles have already been installed, which will anchor the substation and 40 of the 62 wind turbines of the wind farm to the seabed. These cylindrical pieces of steel, each 2.6 meters in diameter and weighing 150 tonnes, are between 18 and 47 meters long. On them are fitted, with millimeter precision, each of the three-legged platforms that will support the turbines.

During this first phase, which has just been completed, the installation of 24 of these platforms has also been completed (about 40% of the total planned). These triangular-based foundations are up to 75 meters high, 25 meters wide and weigh 1,150 tonnes. They are assembled in three stages. The first stage consists of lifting the structure from a transport barge and placing it on site with a crane. During the second stage, the three legs of the frame are inserted into the piles previously fixed to the seabed, ready for the subsequent sealing of the lower parts of the legs.


Thanks to their lattice structure, the platforms have a very limited impact on the environment, facilitating the circulation of water masses and biodiversity, while promoting the artificial reef effect.

During the month of January, the project will continue with the installation of the cabling between wind turbines, depending on weather conditions. In mid-January 2023, work is scheduled to begin on laying the wind farm’s interconnection cable. In total, 90 kilometers of 66 kV high-voltage alternating current interconnection cables will be commissioned. Drilling and pile installation work will resume in the first quarter, when anchoring of the remaining 66 piles will begin. Thus, in the second half of the year, work on the offshore wind platforms will resume and the assembly of the wind turbines will begin.

The contract for the construction of Saint-Brieuc – valued at €350 million – has been the largest order to date executed by the Navantia and Windar partnership in offshore wind power.  This project has generated 1,250 direct jobs in Avilés and Fene. In addition, Navantia-Windar has opened a plant in Brest, France, where the 186 stabbings and intermediate platforms of the transition pieces and the lattice structure for 34 of the 62 structures of the park have been manufactured, generating 250 jobs.

Saint-Brieuc will be the Iberdrola group’s first large offshore wind farm in France, and the company’s fourth of this technology in operation. With almost 500 MW of capacity, it will generate enough clean energy to meet the electricity consumption of 835,000 people, once it comes into operation in 2023. Located some 16 kilometers from the coast, it will cover an area of 75 square kilometers. Its construction represents an overall investment of close to €2.5 billion.