The California Public Utilities Commission (CPUC) has granted a request from the City of Chino Hills to put underground a segment of Southern California Edison's Tehachapi Renewable Transmission Project (TRTP).

The CPUC agreed with the City's assertion that the design of the above-ground line "ignores community values and places an unfair and unreasonable burden on residents."

Currently, the 3.5-mile segment of the 500 kV transmission line running through Chino Hills consists of massive transmission towers reaching nearly 200 feet tall and set in a narrow 150-foot right of way. The CPUC's decision "rectifies that disproportionate burden and finds that it is in the public interest to construct an underground alternative based on a single-circuit, two cables per phase design using cross-linked polyethylene cable."

It will cost approximately $224 million to build the underground Chino Hills portion of the line.

The TRTP is part of a series of new and upgraded high-voltage electric transmission lines to deliver electricity from wind farms in the Tehachapi wind source area north of Los Angeles to customers and the California power grid


Trachte Inc._id1770
Latest Top Stories

The Song Remains The Same: Ontario Seeks More Science Before Lifting Offshore Ban

The Ontario government says the nearly four-year-old offshore wind moratorium will remain in place until the province fully understands the technology’s impact on the environment.


Why States Should Adopt A Renewable Portfolio Standard

A new study analyzes the potential benefits of state renewable energy mandates, as well as recommends what such policies should include.


Sen. Reid Vows To Bring Wind PTC To A Vote By Year's End

Nevada's senior senator provides some encouragement to wind industry advocates during his annual Clean Energy Summit.


Steadily, Wind Turbine OEMs Resume R&D Investment

An increased commitment to research and development will likely lead to wind energy innovation - not to mention a likely increase in patent-protected technology.


Quebec Government Postpones Wind Power RFP; No New Date Scheduled

The request for proposals (RFP) is part of an overall 800 MW wind power tranche that will serve as a bridge to the next phase in the province's energy future.

Renewable NRG_id1934
Canwea_id1984
UnitedEquip_id1995
Future Energy_id2008