RES Americas has filed a lawsuit in Pennsylvania against BP Wind Energy and Mehoopany Wind Energy LLC (MWE), a joint venture between BP and Sempra U.S. Gas & Power.

RES claims the defendants owe the contractor over $55 million in additional expenses accrued in a rush to get the Mehoopany Wind Farm live on Dec. 31, 2012 - just in time to qualify for the wind energy production tax credit (PTC). MWE owns the 141 MW wind farm, located in Wyoming County, Pa., and BP is the operator. The project features 88 GE 1.6 MW wind turbines spread across a 9,000-acre site.

Work on the project was originally slated to begin in October 2011 and end by October 2012. However, RES says the project was delayed from the onset and full construction did not start until February 2012, followed by a series of holdups along the way to completion.

Doug Kilday, the Texas-based lawyer representing RES, says the contractor ultimately documented 272 days of delays and had to squeeze the project from a 12-month process into a five-and-a-half-month period to meet the PTC deadline.

“Each subsequent delay, whether it be a week, two weeks or two days, had a substantial impact because of the initial four-month delay,” Kilday tells NAW, adding that RES believes BP and MWE were to blame for a slew of issues.

For example, RES claims BP and MWE did not provide the contractor with proper permits in the necessary time. In addition, Kilday says RES was hindered by road restrictions and a lack of site access, as well as “unforeseen subsurface conditions” that were not included in MWE’s geotechnical report.

These “crippling delays” and the subsequent time crunch meant that RES had to bring in additional subcontractors and have workers work long hours, holidays and weekends, Kilday adds. RES says the additional costs added up and believes they are the responsibility of BP and MWE.

When reached for inclusion in this story, BP Wind Energy respectfully declined, saying, “The company does not comment on pending litigation." Sempra, which has a half-stake in MWE, did not respond to requests.

However, according to the companies’ response to the lawsuit, as cited in a Sunday Dispatch report, MWE and BP Wind Energy maintain that the extra costs and delays are the result of “RES’ own self-inflicted performance issues.”

In addition, BP Wind Energy and MWE have filed a lawsuit of their own against RES Americas in Texas. The companies are seeking up to $32 million in damages.


Trachte Inc._id1770
Latest Top Stories

Wind And Solar Are Catching Up With Nuclear Power, Says Report

A new report from the Worldwatch Institute says nuclear energy's share of global power production is steadily shrinking. Meanwhile, renewables' share keeps growing.


Could New Desert Plan Spell The End Of California Wind Energy Development?

The California Wind Energy Association says it is disappointed with the draft Desert Renewable Energy Conservation Plan, which was recently released by state and federal agencies.


New U.S. House Bill Includes Wind PTC Extension

U.S. representatives have introduced the Bridge to a Clean Energy Future Act of 2014, which would extend the production tax credit (PTC) and other provisions through 2016.


Utility-Scale Wind And Solar Keep Getting Cheaper

A new study measures the levelized cost of energy from various technologies and suggests that the costs of utility-scale wind and solar power are catching up with those of traditional sources, even without subsidies.


The Song Remains The Same: Ontario Seeks More Science Before Lifting Offshore Ban

The Ontario government says the nearly four-year-old offshore wind moratorium will remain in place until the province fully understands the technology’s impact on the environment.

Renewable NRG_id1934
Canwea_id1984
Future Energy_id2008