in News Departments > FYI
print the content item

Construction of a wind turbine drivetrain testing facility at Clemson University's Restoration Institute will achieve another milestone today, as engineers from Choate Construction pour 1,900 cubic yards of concrete into a pit in order to form the 15 MW test rig foundation.

The building's foundation is almost the equivalent of seven stories deep, and the pit already has approximately 450 tons of reinforcing steel weighing roughly the equivalent of 250 midsize cars, Clemson says, adding that there will be about 3,500 tons of concrete poured into the foundation base. The massive pour will last through the night to take advantage of generally calmer weather conditions and minimize traffic congestion, and is expected to take up to 12 hours.

The operation has taken months of planning and thousands of hours of preparation and field work. Engineers must consider environmental conditions and other factors that could cause an inconsistent flow of concrete. In May 2012, the engineering team from Choate poured the foundation for the smaller test rig. The pour for the 7.5 MW test rig required 750 cubic yards of concrete.

The project involves completely redeveloping an 82,000 square-foot warehouse on the former Navy base. The engineering design was performed by Minneapolis-based AEC Engineering.

In November 2009, Clemson and its partners were awarded a $45 million grant from the U.S. Department of Energy, which was combined with $53 million of matching funds, to build and operate the large-scale testing facility for next-generation wind turbine drivetrains. When complete later this year, the facility will have the capability for full-scale, highly accelerated testing of advanced drivetrain systems for wind turbines in the 5 MW to 15 MW range.

It also will have 50 Hz and 60 Hz testing capability, which means it can accommodate test specimens destined for anywhere in the world, according to Clemson.



Trachte Inc._id1770
Latest Top Stories

Senate Passes Tax Extenders Bill With Wind PTC Extension

The legislation, which passed in the U.S. House earlier this month, will renew the critical production tax credit through the end of 2014 - giving developers only about two weeks left to start construction.


Transmission Study Shows Nebraska Could Handle A Lot More Wind Power

A new report released by the Nebraska Power Review Board finds that the state already has enough infrastructure to accommodate at least 2 GW of additional wind generation.


Can Wind Energy And Birds Coexist? Environmental Group Says Yes

The Environmental Defense Fund, a supporter of responsible wind energy development, points out ways to help mitigate impacts of turbines on birds and bats.


Another Study Finds Wind Turbines Do Not Affect Nearby Property Values

Research conducted by the University of Guelph focused on regions in Ontario, and the conclusion echoes that of previous studies.


Too Little, Too Late? U.S. House Approves Wind PTC Extension

The U.S. House of Representatives has passed a tax extenders package that would renew the wind production tax credit (PTC) and about 50 other expired tax breaks through 2014. The wind industry argues the short-term fix is virtually no fix at all.

Hybrid Energy Innovations 2015