Even with the wind energy production tax credit (PTC) extended, only 3 GW to 4 GW of new wind power is likely to enter commercial operation by the end of 2013, compared to the approximately 12 GW that came online in 2012, analysts at research firm Industrial Info Resources predict.

In fact, between 8 GW and 8.8 GW of new wind energy generation could reach the construction stage this year, with construction and operations extending into 2014, says Shane Mullins, the firm's vice president of product development for the power industry.

"An extended PTC puts the onus on wind power developers to quickly revisit and reactivate the project pipeline, which has been on hold for a while as companies focused on completing projects by year-end 2012," Mullins says. "Projects that could not be completed by year-end 2012 were placed on hold. Now, those projects need to be revived and reviewed for viability."

According to Mullins, there are many factors that will likely prevent a repeat of last year's record level of wind project development.

For one, he says, many utilities are ahead of the curve on meeting their state renewable portfolio standards. In addition, many bankable projects that were being developed for a 2013 kickoff were moved into 2012 in order to take advantage of the PTC.

Another challenge is that due to policy uncertainty, many developers and equipment manufacturers slashed staff and placed projects on hold.

"Developers and manufacturers need time to gear up, so the new PTC extension will be largely felt in the second half of 2013 and will not repeat what happened in 2012, when new development dropped sharply in favor of finishing projects that could operate commercially by Dec. 31, 2012,” Mullins explains.




Trachte Inc._id1770
Latest Top Stories

Setting The Record Straight: How Many Birds Do Wind Turbines Really Kill?

Several peer-reviewed studies are more or less in agreement with avian mortality rates caused by wind turbines. However, one study, which is wildly off from the others, is most often cited in the media. Why?


Six Takeaways From The IRS' Start Of Construction Guidance: What You Need To Know

The IRS recently issued guidance to wind developers to further spell out what "start of construction" means. Will you be covered?


Eagle Take Permits For Wind Farms - Will They Fly?

Now that the U.S. Fish and Wildlife Service has issued the first permit allowing the legal take of eagles, can wind developers expect more certainty in the agency's application process?


Despite 2013 Challenges, U.S. Wind Power Reaches All-Time Low Price

In a new report, the U.S. Department of Energy details the highs and lows of the country's wind industry last year, and the agency maintains that the U.S. sector remains strong.


Mexico On Pace To Set New Renewables Investment Record

A new report says the country has spent $1.3 billion on clean energy in the first half of 2014 and could end up seeing a record year. Furthermore, wind power is slated for significant growth in the region.

Canwea_id1984
Renewable NRG_id1934
UnitedEquip_id1995
Tower Conference_id1965