Minnesota Power Completes Bison Wind Energy Center
in News Departments > Projects & Contracts
print the content item
Minnesota Power has completed phases two and three of the company's 292 MW Bison Wind Energy Center.

The second and third phases of the Bison project total 210 MW and are now operational. Together, Bison 2 and 3 consist of 70 3 MW Siemens direct-drive wind turbines with 265-foot towers.

The Bison project was launched in 2010 with the 82 MW Bison 1 wind farm, which consists of 31 turbines built over two years.

Minnesota Power is moving the wind energy from North Dakota to Duluth, Minn., over a 465-mile direct-current transmission line that the company purchased in 2009. That purchase enabled the utility to phase out a long-term contract to buy coal-based electricity from the Young Station in Center, N.D., and replace it with wind energy.

The final stage of the project launch involves control testing that demonstrates that the Bison project can function as a “wind park,” with all three phases working together. The Midwest Independent Transmission System Operator will be involved in integrating the completed wind park into the regional power grid.

Don't miss the latest wind energy news -- register to receive NAW's news headlines.



Latest Top Stories

As U.S. DOJ Investigates, Duke Works Adaptive Management Plan

With previous golden eagle fatalities reported at two company-owned wind farms in Wyoming, Duke Energy Renewables is going to great lengths to protect raptors.


DOE To Recast Landmark 20% Wind Energy Report; Study Looks Back, Ahead

The U.S. Department of Energy will update its 20% Wind Energy By 2030 report, which indicated increased levels of wind penetration for the U.S. is not only possible but feasible.


Wind Energy Procurement Top Of Mind For Big-Name Companies

With greater frequency, top-tier companies are discovering the economic and environmental power of wind energy and upping their investments in the resource.


WINDPOWER Panelists Issue A Call To Arms: Protect RPS Mandates

Votes on several legislative bills concerning state renewable portfolio standards (RPS) are nearing. How can you help protect and maintain these development drivers?


Wind Industry Still Awaits First Eagle-Take Permit Under BGEPA

The first wind developer to apply for a take permit under the Bald and Golden Eagle Protection Act has withdrawn its application.

Related Stories
Hse SandyHook
Follow Us on Twitter
NAW Mobile

Upwind Solutions_id1629
Power Climber_id1659
UEA_id1698
SandC Electric_id1674
NRG Systems JWT_id1677
Trachte Inc._id484
AWEA_id1658
Castrol